Procedures written for commissioning, cool down, and start-up of a new ship unloading facility.
Commissioning and start-up of LNG Train 4.
Commissioning and start-up of RasGas LNG Train 5.
Commissioning and start-up of a 2500 TPD Methanol facility.
Commissioning and start-up of a 300,000 TPY MTBE facility.
Produced Modules for the LNG Receiving Terminal training program.
Commissioning and start-up of the LNG receiving terminal and re-gasification facility.
Procedures written for pre-commissioning and commissioning of two Conoco-Phillips LNG trains.
Commissioning and start-up of the LNG facility feed gas pre-treatment facility.
Commissioning and start-up of Suncor Energy’s demonstration shale oil facility.
Commissioning and start-up of a 1200 TPD Methanol facility.
Commissioning and start-up of NLNG LNG Train 3.